Project Overview
The Vancouver Fraser Port Authority has earned Envision Platinum verification for the Holdom Overpass Project in Burnaby, British Columbia, Canada, recognizing its comprehensive approach to sustainability and resilience throughout project planning, design, and construction. This marks the port authority’s third Envision-verified project, with all three achieving the Envision Platinum level. This project is part of the Burnaby Rail Corridor Improvements Project, a package of road and rail infrastructure upgrades that the port authority is delivering to improve connectivity, safety, and mobility. The Holdom Overpass Project will extend Holdom Avenue to Douglas Road with a new four-lane overpass, creating safer routes for pedestrians and cyclists, improved signalized intersections, utility improvements, environmental enhancements, and closure of the Douglas Road rail crossing once the overpass is open.
The purpose of the Holdom Overpass Project is to improve safety and connectivity in a busy rail corridor while strengthening long-term trade capacity and efficiency. By replacing the Douglas Road at-grade rail crossing with a new overpass, and adding safer routes for pedestrians and cyclists, the project will help reduce conflicts between trains, vehicles, and people while supporting more reliable movement through the area.
The project team chose to use the Envision Sustainable Infrastructure Framework to support the port authority’s broader corporate commitment to delivering infrastructure that advances sustainability, resilience, and community benefit. Envision, which was designed to promote more sustainable, resilient, and equitable infrastructure projects, is comprised of 64 sustainability and resiliency indicators (called credits) which are organized within five categories: Quality of Life, Leadership, Resource Allocation, Natural World, and Climate and Resilience. Together, the categories and credits address materials, energy, conservation, community development, planning, collaboration, human well-being, mobility, and more. Using Envision helped the team apply a consistent, third-party framework to guide decision-making, track performance, and demonstrate how the Holdom Overpass Project aligns with the port authority’s long-term sustainability goals.
Construction began in December 2024, and the overpass is scheduled to open to the public early next year.

Verified Sustainability Achievements
Improve Public Health & Safety — The Holdom Overpass Project substantially improves public health and safety by replacing the existing at-grade rail crossing with grade-separated infrastructure, eliminating conflicts between trains, vehicles, pedestrians, and cyclists while providing more reliable routes for emergency response. The design introduces protected walking and cycling facilities, improved crossings, lighting, and other features that create safer, more accessible conditions and encourage active transportation. Beyond the project site, improved traffic flow reduces vehicle idling and associated emissions supporting better health for the surrounding community.
Support Sustainable Transportation — This project encourages sustainable and active transportation by creating safer, more convenient connections for people walking, cycling, and using public transit. Located near the Holdom SkyTrain station and connecting with local bus service and the Central Valley Greenway (a key regional greenway for active transportation users), the project introduces separated multi-use pathways, improved pedestrian and cycling links, and amenities such as bike racks, seating, lighting, and wayfinding that make active travel more accessible and inviting. The project also addresses existing gaps in the walking and cycling network and creates stronger connections across the rail corridor, integrating these improvements with Burnaby’s broader transportation system. These investments expand transportation choices and help create a safer, better-connected multimodal network that supports more sustainable ways of getting around.
Incorporate First Nations and Community Input — The Holdom Overpass Project team involved the local community throughout planning, design, and construction using a structured engagement process that began with mapping the people, businesses, organizations, and rights holders affected by or interested in the project. Three phases of public engagement, ongoing correspondence, targeted meetings, and consultation with First Nations provided multiple opportunities to raise concerns and shape project outcomes. Feedback directly informed improvements such as wider pedestrian and cycling paths, safer crossings and signage, maintained access to properties, refinements to construction detours, and the inclusion of First Nations art in public spaces. The project also established partnerships with the City of Burnaby and the Canadian National Railway Company (CN) helping ensure that decisions reflected a broad range of community and operational perspectives.
Preserve Historic & Cultural Resources — The Holdom Overpass Project team took a thoughtful approach to preserving historic and cultural resources through archaeological assessment and extensive consultation with First Nations. While archaeological investigations did not identify archaeological materials within the project footprint, the project established procedures to protect potential discoveries during construction and worked with First Nation communities to identify cultural values extending beyond formally registered resources. These considerations informed environmental protection and landscape measures as well as First Nations art and interpretive elements integrated into the project.
Enhance Public Spaces — The Holdom Overpass Project transforms portions of an industrial and rail-adjacent corridor into more accessible, inviting, and environmentally integrated community spaces. The project improves the Central Valley Greenway and adds new plazas, lookouts, seating areas, multi-use paths, landscaping, and gathering spaces that strengthen connections throughout the area. Frist Nations art and interpretive signage add cultural and educational value, while native plantings and habitat restoration improve previously degraded areas along the greenway and Still Creek corridor. Together, these improvements create new opportunities for people to walk, cycle, gather, and experience the area while strengthening its ecological and community character.
Maximize Resilience — The Holdom Overpass Project incorporates resilience into its design and long-term planning to better withstand climate-related and other hazards. A comprehensive risk assessment informed strategies to address risks such as flooding, extreme temperatures, snow and ice, seismic and geotechnical conditions, erosion, and power disruption. These considerations influenced features including climate-responsive drainage, resilient landscaping, structural design, and provisions for reliable operation during disruptive conditions.

Quotes
“The Envision Platinum award builds on our proven track record of delivering high-quality, sustainable infrastructure that supports Canada’s trade needs while creating lasting benefits for communities and the environment. The Holdom Overpass Project continues that legacy and reflects what’s possible through strong collaboration with First Nations, the City of Burnaby, CN, the Government of Canada, and our design-build contractor Aecon-Gateway Infrastructure Group Partnership.“– Jennifer Natland, Vice President of Properties and Development, Vancouver Fraser Port Authority
“I am humbled to have had the opportunity to contribute to the sustainability of a project with national significance, delivering meaningful local benefits. As part of the Mott MacDonald Owner’s Engineer team, and Lead ENV SP, I had the pleasure of working closely with the port authority to help realise the full sustainability potential of the project. The Platinum award reflects the collective effort of the broader project team to integrate sustainability throughout project development and delivery.“– Scott Smith, Senior Consultant, Mott MacDonald
“ISI congratulates the Vancouver Fraser Port Authority and the entire Holdom Overpass project team on achieving Envision Platinum verification. This project demonstrates how infrastructure can do more than solve a transportation challenge — it can improve safety, expand active transportation options, strengthen resilience, and create lasting value for the surrounding community. The team’s thoughtful approach to engagement, sustainability, and long-term performance sets an excellent example for transportation projects across Canada and beyond.“– Kailey Eldredge, Verification Director, Institute for Sustainable Infrastructure
PROJECT DETAILS AT-A-GLANCE
Title: Holdom Overpass Project
Location: Burnaby, British Columbia, Canada
Envision Rating: Platinum
Envision Award Date: September 21, 2026
Envision Version: v3
Project Owner: Vancouver Fraser Port Authority
Project Sector: Transportation
Project Type: Bridge
Project Type: Bridge
Lead Envision Firm: Mott MacDonald
Project Partners: City of Burnaby, Canadian National Railway Company (CN)
Total Project Cost: C$197 million
Project Status: in construction
Project Website: https://www.portvancouver.com/holdomoverpass